Maryland Line to Five Forks

115 kV Line Rebuild

0

Miles of Line

0 kV

Project Need

  • This circuit is among the lowest reliability performers on the BGE transmission systems. Rebuilding this line addresses multiple reliability concerns including; aging infrastructure, aging conductor splices and avian interference

Project Description

  • The scope of the project is to remove the existing two single-circuit 115 kV tower lines (CKT 110901-1 & 110901-2) and replace with a new single-circuit monopole structure line
  • Overall project length is approximately 1.8 miles
  • This project is subject to PSC approval and design changes

Resources

Timeline

Fall 2018

Begin Design and Engineering

Fall 2018

Begin Design and Engineering

Summer 2019

Complete Design and Engineering

Fall 2020

PSC Evidentiary Hearing

January 11, 2020

CPCN Approval

August 2021

Construction Start

December 2021

Project Service Date

Left-Click and DRAG Slider Bar to Reveal Existing and Proposed Conditions

Photo Simulation

View looking north from Whiteford Rd. This project is subject to PSC approval and design changes.

Viewpoint Location Map

Construction Sequence

Construction sequence graphics are intended to provide an overview of the typical construction sequence for a project. These graphics are used to give stakeholders a general idea of what to expect regarding this project’s construction process and effort. This project is subject to PSC approval and design changes.

Maryland Line to Five Forks

Right-of-Way Path